PHASE 5: construction work on the Oudedijk road network will start.

What

In this phase, work will be undertaken on the bypass on the side of the Ketel Dyke.

Duration

Work will be carried out in June 2018.

Impact on traffic

The work will mean that traffic will not be able to use bridge 2 and the bypass to the Ketel Dyke will be closed.
Traffic travelling in the direction of Ketel Dyke from Oudedijk will need to use the roundabout.
Traffic heading towards St Antoniusweg/Molenweg, coming from the North Waaslandhaven slip road (R2 direction Liefkenshoek Tunnel), will be diverted via Oudedijk/St Annalaan.