PHASE 4 - Re-profiling of railway bridges and further construction on the road network on the St. Antoniusweg side

What

Re-profiling of railway bridges and further construction on the road network on the St. Antoniusweg side

Duration

The work will begin in April 2018 and will last until June 2018.

Impact on traffic

During this phase, connections from the North Waaslandhaven complex to St Antoniusweg will be closed. The traffic to and from the Kieldrechtsluis will be diverted via Molenweg.
The traffic to St Antoniusweg, coming from the North Waaslandhaven exit (R2 direction Beveren) will be diverted via Molenweg.
Traffic heading towards the R2 Liefkenshoek Tunnel, coming from St Antoniusweg/Molenweg, will be diverted via the St Annalaan roundabout and bridge 1.
During this phase, work will also be carried out on Ploegweg for a week. The traffic will then be routed via the R2 (slip road 11 North Waaslandhaven and slip road 10 South Waaslandhaven).